Daily hot cost report template
A studio accounting daily hot cost sheet with standard film account codes (2000–3800), budgeted vs. actual labour, 1x/1.5x/2x hours, meal penalties, kit rentals, fringes, and variance.
Free. No sign-up, no email. · Excel (.xlsx) auto-calculates Daily Variance (Budget − Actual), Estimated Fringes %, Total Loaded Labour, and Day Totals across all departments.

Studio sheet preview
| Acct # | Department | Crew | Daily Budget | 1x Hrs | 1.5x OT | 2x DT | MP $ | Kit / Box | Daily Actual | Variance | Variance Driver |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 3300 | Camera | 7 | $4,400 | 56.0 | 14.0 | 0.0 | $0 | $350 | $4,280 | +$120 | Wrapped on schedule |
| 3400 | Grip | 6 | $3,200 | 48.0 | 12.0 | 3.0 | $150 | $250 | $3,650 | -$450 | Company move + late M1 |
| 3500 | Electric / Lighting | 6 | $3,150 | 48.0 | 12.0 | 3.0 | $150 | $200 | $3,580 | -$430 | Pre-light & night ext. |
What is in the template
- Standard film chart-of-accounts codes (2000 Production Staff through 3800 Catering & Craft) ready to map into Movie Magic Budgeting
- Daily budgeted labour vs. actual labour, crew headcount, 1x/1.5x/2x hours, meal penalties, and kit/box rentals
- Live Excel variance formulas (Budget − Actual) plus configurable Est. Fringe % calculation row
- Variance driver column to document company moves, late meals, or extra setups for producers
- Accountant & UPM / Line Producer approval strip with payroll-is-final disclaimer
How to fill it in
- Enter daily department budgets & fringe %Drop each department's daily labour allowance from your Movie Magic or Showbiz budget and set your estimated fringe rate (e.g. 24%).
- Tally daily hours & allowancesEnter crew headcount, straight (1x), overtime (1.5x), double-time (2x) hours, meal penalty counts, and kit/box rentals from approved timesheets.
- Review variance & fringesThe Excel workbook computes Variance (negative = over budget), Estimated Fringes, and Total Loaded Daily Cost automatically.
- Annotate drivers & send by 9 AMNote what drove every red variance (extra setup, weather hold, late lunch) and send to the Line Producer and UPM before call.
What to watch for
- Always state clearly whether your daily budget column includes or excludes payroll fringes — mixing the two distorts variance by 20–30%.
- Hot costs only flag overages *after* the day wraps. Use ArosTime's free Wrap Cost Simulator on set before agreeing to one more setup.
- Track kit/box rentals separately from base labour so weekly kit caps don't skew your daily overtime trend.
Pair with free set calculators
Estimate union overtime, meal penalties and wrap costs across 35 CA, US & UK agreements before calling one more setup.
Get hot costs automatically — plus simulate wrap live on set
ArosTime computes daily hot costs automatically from approved timesheets and crew rates, emails producers at 9 AM, AND includes a live on-set Wrap Simulator so UPMs see overtime before it happens. Free forever for 1 production and up to 25 crew.
Questions people ask
Does the Excel (.xlsx) hot cost report calculate variances and fringes?
Yes. Entering Budgeted Labour, Actual Labour, Kit/Box Rentals, and your Fringe % automatically computes per-department Variance (Budget − Actual), Total Daily Actual, Estimated Fringes, Total Loaded Labour, and % of Budget.
Do the account codes match Movie Magic Budgeting?
Yes — it comes pre-populated with common North American production account blocks (2000 Production Staff, 2100 ADs, 3300 Camera, 3400 Grip, 3500 Electric, etc.) that you can edit to match your exact COA.
How is a hot cost different from a weekly cost report?
A cost report is the accountant's full weekly ledger (actuals + commitments + EFC across all accounts). A hot cost is the fast next-morning labour pulse so the UPM can adjust tomorrow's schedule.